90
|
|

2/10/89 cutting shell plating fr 91 starboard

2/10/89 portside shell plate removals alongside keel fr 110-104
|
91
|
|

2/10/89 piping & bottom of keelson, portside fr 109

2/10/89 starboard shell plating removals, starboard fr 109-104
|
92
|
|

2/14/89 plate removals, starboard fr 107

3/8/89 new deck plating in place, fr 129-132, stern
|
93
|
|

3/9/89 sandblasting port bow forefoot

3/6/89 renewed hatches aft of crew's galley
|
94
|
|

3/10/89 neutralizing chloride contamination treatment solution

3/7/89 plate removals portside stern fr 128
|
95
|
|

3/15/89 doors & hatches ready for re-installatio n

3/16/89 artifacts found in D-108, D-18-M
|
96
|
|

3/16/89 cropping port quarter fr 125-130

3/22/89 scaffolding & removed plating starboard stern
|
97
|
|

4/3/89 transverse flooring removed from portside upper blister

4/5/89 foremast tripod on drydock floor
|
98
|
|

4/5/89 foremast tripod secondary battery top inside looking starboard

4/5/89 foremast tripod main battery director & lifting padeyes
|
99
|
|

4/27/89 gun mount support & splinter shield marking, 01 level

5/5/89 third refitting of smokestack vent umbrella
|
100
|
|

5/15/89 40mm quad mounts in shipyard warehouse
awaiting installation

5/15/89 portside bow partially primed
|
101
|
|

5/15/89 new upper blister swash bulkheads, portside

5/15/89 new starboard gun mount on 02 level starboard
|
102
|
|

5/19/89 new SK antenna in shipyard warehouse

5/23/89 starboard, aft to forward
|
103
|
|

6/23/89 Mark 51 director base ring installed on RS room fr 72-73

7/13/89 splinter screen atop portside 40mm clipping room
fr 99-100
|
104
|
|

7/25/89 replacing foretop on ship

7/27/89 starboard stern hull stripe coat
|
105
|
|

8/7/89 removal from drydock

8/9/89 ship at pierside, Todd Shipyard
|
106
|
|

8/9/89 stern starboard markings

9/26/89 blasted & primed main deck, bow
|
107
|
|

10/13/89 restoration of 20mm guns
|